The European Bank for Reconstruction and Development (EBRD) is proposing a minimum bid bond of €200,000 for developers competing in Ukraine's first RAMP-UP wind energy auction, which has been delayed until February or March 2027 because of outstanding legislative changes.
The proposed requirement is based on a minimum bid size of 20 megawatts (MW) and a bid bond of €10 per kilowatt, Adil Hanif, who heads the EBRD team responsible for the programme's design, told Ukraine Rebuild Newswire in an interview.